Question in Korean (English title coming soon)
옹벽형날개벽 앞굽철근배근시 125간격으로 배근하고싶은데 어디서 조정하는지 알고싶습니다.
Answer
안녕하세요. 한길아이티입니다. 현재 앞굽부분에도 2cycle를 적용시켜 뒷굽과 같이 적용할려고 작업중에 있습니다. 2~3일정도 더 소요될 예정입니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | ACulvert | #268543 | Pile calculation report | 328 | 2026-09-28 |
| Answered | ACulvert | #268536 | Setting section changes in culvert | 167 | 2026-09-28 |
| Answered | ACulvert | #268524 | Design check not performed at wall center | 215 | 2026-09-27 |
| Answered | ACulvert | #268523 | Applying moving vehicle loads | 233 | 2026-09-27 |
| Answered | ACulvert | #268522 | Question about pile layout | 261 | 2026-09-23 |
| Answered | ACulvert | #268521 | Question about features | 128 | 2026-09-23 |
| Answered | ACulvert | #268510 | Question about joint check in Excel report output | 180 | 2026-09-22 |
| Answered | ACulvert | #268499 | Error in STM analysis of corner region | 140 | 2026-09-22 |
| Answered | ACulvert | #268471 | Launching the culvert program | 59 | 2026-09-18 |
| Answered | ACulvert | #268442 | All lines are displayed as dashed lines, what should I do? | 138 | 2026-09-17 |
| Answered | ACulvert | #268429 | Question about U-type underpass | 126 | 2026-09-17 |
| Answered | ACulvert | #268424 | Load position when applying railway loads to an underpass | 230 | 2026-09-17 |
| Answered | ACulvert | #268417 | Changing girder dimensions | 147 | 2026-09-17 |
| Answered | ACulvert | #268396 | Incorrect section check location for horizontal rebar | 174 | 2026-09-16 |
| Answered | ACulvert | #268376 | Question about segment settings for U-type retaining wall | 185 | 2026-09-15 |
| Answered | ACulvert | #268343 | Question about culvert drawing output | 126 | 2026-09-15 |
| Answered | ACulvert | #268337 | Inquiry about checking retaining-wall-type wing walls | 300 | 2026-09-14 |
| Answered | ACulvert | #268330 | About drawing output | 150 | 2026-09-14 |
| Answered | ACulvert | #268318 | Some blocks not displayed | 136 | 2026-09-14 |
| Answered | ACulvert | #268317 | Tank load for surcharge and moving loads | 335 | 2026-09-14 |