Question in Korean (English title coming soon)
1. 배력철근검토에서 사용철근 개수가 잘못 들어가는것 같습니다. 2. output 기능,붕괴 sheet에 data가 안물리는거 같습니다. 확인 부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 오류를 확인 하였습니다.금일 패치에 수정하여 적용토록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | ACulvert | #268543 | Pile calculation report | 328 | 2026-09-28 |
| Answered | ACulvert | #268536 | Setting section changes in culvert | 168 | 2026-09-28 |
| Answered | ACulvert | #268524 | Design check not performed at wall center | 215 | 2026-09-27 |
| Answered | ACulvert | #268523 | Applying moving vehicle loads | 233 | 2026-09-27 |
| Answered | ACulvert | #268522 | Question about pile layout | 261 | 2026-09-23 |
| Answered | ACulvert | #268521 | Question about features | 128 | 2026-09-23 |
| Answered | ACulvert | #268510 | Question about joint check in Excel report output | 181 | 2026-09-22 |
| Answered | ACulvert | #268499 | Error in STM analysis of corner region | 140 | 2026-09-22 |
| Answered | ACulvert | #268471 | Launching the culvert program | 59 | 2026-09-18 |
| Answered | ACulvert | #268442 | All lines are displayed as dashed lines, what should I do? | 138 | 2026-09-17 |
| Answered | ACulvert | #268429 | Question about U-type underpass | 126 | 2026-09-17 |
| Answered | ACulvert | #268424 | Load position when applying railway loads to an underpass | 230 | 2026-09-17 |
| Answered | ACulvert | #268417 | Changing girder dimensions | 147 | 2026-09-17 |
| Answered | ACulvert | #268396 | Incorrect section check location for horizontal rebar | 176 | 2026-09-16 |
| Answered | ACulvert | #268376 | Question about segment settings for U-type retaining wall | 185 | 2026-09-15 |
| Answered | ACulvert | #268343 | Question about culvert drawing output | 127 | 2026-09-15 |
| Answered | ACulvert | #268337 | Inquiry about checking retaining-wall-type wing walls | 301 | 2026-09-14 |
| Answered | ACulvert | #268330 | About drawing output | 151 | 2026-09-14 |
| Answered | ACulvert | #268318 | Some blocks not displayed | 136 | 2026-09-14 |
| Answered | ACulvert | #268317 | Tank load for surcharge and moving loads | 335 | 2026-09-14 |