Load calculation
이 암거의 경우 토피가 포장층보다 작은 경우인데요.. 하중계산에서 토압 Wh1값이 잘못 계산된것 같습니다. 암거 윗부분 포장층까지만 계산이 되어야 되는데... 지금 이 계산서를 보면 포장층 전부 계산이 되어 있습니다.
Answer
안녕하세요. 한길아이티입니다. 수정하여 패치에 적용토록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | ACulvert | #268543 | Pile calculation report | 329 | 2026-09-28 |
| Answered | ACulvert | #268536 | Setting section changes in culvert | 170 | 2026-09-28 |
| Answered | ACulvert | #268524 | Design check not performed at wall center | 215 | 2026-09-27 |
| Answered | ACulvert | #268523 | Applying moving vehicle loads | 234 | 2026-09-27 |
| Answered | ACulvert | #268522 | Question about pile layout | 261 | 2026-09-23 |
| Answered | ACulvert | #268521 | Question about features | 128 | 2026-09-23 |
| Answered | ACulvert | #268510 | Question about joint check in Excel report output | 181 | 2026-09-22 |
| Answered | ACulvert | #268499 | Error in STM analysis of corner region | 142 | 2026-09-22 |
| Answered | ACulvert | #268471 | Launching the culvert program | 59 | 2026-09-18 |
| Answered | ACulvert | #268442 | All lines are displayed as dashed lines, what should I do? | 138 | 2026-09-17 |
| Answered | ACulvert | #268429 | Question about U-type underpass | 126 | 2026-09-17 |
| Answered | ACulvert | #268424 | Load position when applying railway loads to an underpass | 231 | 2026-09-17 |
| Answered | ACulvert | #268417 | Changing girder dimensions | 147 | 2026-09-17 |
| Answered | ACulvert | #268396 | Incorrect section check location for horizontal rebar | 176 | 2026-09-16 |
| Answered | ACulvert | #268376 | Question about segment settings for U-type retaining wall | 186 | 2026-09-15 |
| Answered | ACulvert | #268343 | Question about culvert drawing output | 127 | 2026-09-15 |
| Answered | ACulvert | #268337 | Inquiry about checking retaining-wall-type wing walls | 301 | 2026-09-14 |
| Answered | ACulvert | #268330 | About drawing output | 151 | 2026-09-14 |
| Answered | ACulvert | #268318 | Some blocks not displayed | 136 | 2026-09-14 |
| Answered | ACulvert | #268317 | Tank load for surcharge and moving loads | 335 | 2026-09-14 |