About haunch reinforcement
건교부 표준단면도에 보면 사보강에 대해 언급이 되어 있는데..(페이지 E4-1) 여기에 보면 사보강 하는 위치가 암거 중심을 기준으로 반은 직선 철근을 배근 하고 나머지 반을 사보강 하는것 같은데.. 컬버트에서는 그렇지 않고 암거 전체를 사보강 해 버리는데.. 확인 부탁 드립니다.
Answer
안녕하세요. 한길아이티입니다. 암거의 길이에 따라 사보강의 범위가 바뀌게 됩니다. 또한 설계선택사항에 옵션으로 사보강의 범위 정하게 되어 있습니다. 자세한 내용을 첨부파일을 보내주시면 다시 검토해 보겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | ACulvert | #268543 | Pile calculation report | 329 | 2026-09-28 |
| Answered | ACulvert | #268536 | Setting section changes in culvert | 173 | 2026-09-28 |
| Answered | ACulvert | #268524 | Design check not performed at wall center | 216 | 2026-09-27 |
| Answered | ACulvert | #268523 | Applying moving vehicle loads | 236 | 2026-09-27 |
| Answered | ACulvert | #268522 | Question about pile layout | 261 | 2026-09-23 |
| Answered | ACulvert | #268521 | Question about features | 130 | 2026-09-23 |
| Answered | ACulvert | #268510 | Question about joint check in Excel report output | 184 | 2026-09-22 |
| Answered | ACulvert | #268499 | Error in STM analysis of corner region | 143 | 2026-09-22 |
| Answered | ACulvert | #268471 | Launching the culvert program | 59 | 2026-09-18 |
| Answered | ACulvert | #268442 | All lines are displayed as dashed lines, what should I do? | 139 | 2026-09-17 |
| Answered | ACulvert | #268429 | Question about U-type underpass | 126 | 2026-09-17 |
| Answered | ACulvert | #268424 | Load position when applying railway loads to an underpass | 236 | 2026-09-17 |
| Answered | ACulvert | #268417 | Changing girder dimensions | 152 | 2026-09-17 |
| Answered | ACulvert | #268396 | Incorrect section check location for horizontal rebar | 182 | 2026-09-16 |
| Answered | ACulvert | #268376 | Question about segment settings for U-type retaining wall | 191 | 2026-09-15 |
| Answered | ACulvert | #268343 | Question about culvert drawing output | 128 | 2026-09-15 |
| Answered | ACulvert | #268337 | Inquiry about checking retaining-wall-type wing walls | 305 | 2026-09-14 |
| Answered | ACulvert | #268330 | About drawing output | 153 | 2026-09-14 |
| Answered | ACulvert | #268318 | Some blocks not displayed | 139 | 2026-09-14 |
| Answered | ACulvert | #268317 | Tank load for surcharge and moving loads | 338 | 2026-09-14 |