Rebar arrangement at cutoff points

단절점부 철근배치시 위치가 주철근 밖으로 밀려서 배치됩니다. 참고로 도로교 설계기준에서는 0.4R~0.65R사이에 배치(도로교설계기준해설-2003(718p.~720p.)되어야합니다. 임의대로 위치설정을 할수있는 방법은 없는지.. 검토하시고 연락 기다리겠습니다. [개인정보]

Answer

안녕하세요. 한길아이티입니다. 단절점부 보강철근 기준인 0.4로 배치한 경우입니다.입력한 단면에서 하부 슬래브두께(400), 벽체두께(300), 피복(100)으로 배근되어 주철근 밖으로 나간경우 입니다. 해석상 단절점 보강이 필요하므로 피복두께를 조정하셔야 될듯합니다. 0.4R은 말씀하신거와 같이 정해진 값이라서 프로그램내에서는 임의 수정을 지원하지 않고 있습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredACulvert#268543Pile calculation report3292026-09-28
AnsweredACulvert#268536Setting section changes in culvert1732026-09-28
AnsweredACulvert#268524Design check not performed at wall center2162026-09-27
AnsweredACulvert#268523Applying moving vehicle loads2382026-09-27
AnsweredACulvert#268522Question about pile layout2612026-09-23
AnsweredACulvert#268521Question about features1302026-09-23
AnsweredACulvert#268510Question about joint check in Excel report output1842026-09-22
AnsweredACulvert#268499Error in STM analysis of corner region1432026-09-22
AnsweredACulvert#268471Launching the culvert program592026-09-18
AnsweredACulvert#268442All lines are displayed as dashed lines, what should I do?1402026-09-17
AnsweredACulvert#268429Question about U-type underpass1262026-09-17
AnsweredACulvert#268424Load position when applying railway loads to an underpass2372026-09-17
AnsweredACulvert#268417Changing girder dimensions1522026-09-17
AnsweredACulvert#268396Incorrect section check location for horizontal rebar1832026-09-16
AnsweredACulvert#268376Question about segment settings for U-type retaining wall1912026-09-15
AnsweredACulvert#268343Question about culvert drawing output1282026-09-15
AnsweredACulvert#268337Inquiry about checking retaining-wall-type wing walls3062026-09-14
AnsweredACulvert#268330About drawing output1532026-09-14
AnsweredACulvert#268318Some blocks not displayed1402026-09-14
AnsweredACulvert#268317Tank load for surcharge and moving loads3392026-09-14
Sign in to ask