Inquiry about distribution rebar quantity

자꾸 배력철근으로 귀찮게 해서 죄송합니다. 도로교 설계기준 2003 P234 (4) 2)의 경우 토피가 0.6m 이상 흙이 덮이는 암거에 대해서는 그 백분율을 20%로 한다고 규정되어 있으므로, 활하중을 직접 재하한 경우라도 이 규정을 적용해야 하는것이 아닌지 생각되는군요. 슬래브의 경우도 정모멘트 구간에만 P231의 식을 적용하는것이 타당하며, 나머지 구간은 50%만 배근하고 있읍니다. 지간이 짧은 암거의 경우 식에 의한 계산을 하다보면 35%도 적용되는 경우가 있는데 이것을 전 암거 전구간 배치하는 것은 너무 과다한 배근이 아닌가 생각됩니다. 검토 부탁드립니다. 수고하십시요....

Answer

안녕하세요. 한길아이티입니다. 전화로 답변드렸습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredACulvert#268543Pile calculation report3292026-09-28
AnsweredACulvert#268536Setting section changes in culvert1742026-09-28
AnsweredACulvert#268524Design check not performed at wall center2162026-09-27
AnsweredACulvert#268523Applying moving vehicle loads2382026-09-27
AnsweredACulvert#268522Question about pile layout2612026-09-23
AnsweredACulvert#268521Question about features1302026-09-23
AnsweredACulvert#268510Question about joint check in Excel report output1842026-09-22
AnsweredACulvert#268499Error in STM analysis of corner region1442026-09-22
AnsweredACulvert#268471Launching the culvert program592026-09-18
AnsweredACulvert#268442All lines are displayed as dashed lines, what should I do?1402026-09-17
AnsweredACulvert#268429Question about U-type underpass1262026-09-17
AnsweredACulvert#268424Load position when applying railway loads to an underpass2372026-09-17
AnsweredACulvert#268417Changing girder dimensions1522026-09-17
AnsweredACulvert#268396Incorrect section check location for horizontal rebar1832026-09-16
AnsweredACulvert#268376Question about segment settings for U-type retaining wall1922026-09-15
AnsweredACulvert#268343Question about culvert drawing output1282026-09-15
AnsweredACulvert#268337Inquiry about checking retaining-wall-type wing walls3062026-09-14
AnsweredACulvert#268330About drawing output1532026-09-14
AnsweredACulvert#268318Some blocks not displayed1402026-09-14
AnsweredACulvert#268317Tank load for surcharge and moving loads3392026-09-14
Sign in to ask
Inquiry about distribution rebar quantity · aroad