AnsweredACulvertQ&A #2253572004-10-07 04:16 · Views 103

Please review

접속슬래브의 철근상세에서 주철근과 배력철근이 반대로 표기가 되는데 검토 좀 부탁드립니다... 수고하십시오.//

Answer

안녕하세요. 한길아이티입니다. 제대로 표기되고 있습니다. 장변이 배력철근이고 단변이 주철근입니다. 접속슬래브 상세입력에서 평면도를 확인해 보시기 바랍니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredACulvert#268543Pile calculation report3292026-09-28
AnsweredACulvert#268536Setting section changes in culvert1742026-09-28
AnsweredACulvert#268524Design check not performed at wall center2172026-09-27
AnsweredACulvert#268523Applying moving vehicle loads2392026-09-27
AnsweredACulvert#268522Question about pile layout2632026-09-23
AnsweredACulvert#268521Question about features1302026-09-23
AnsweredACulvert#268510Question about joint check in Excel report output1852026-09-22
AnsweredACulvert#268499Error in STM analysis of corner region1442026-09-22
AnsweredACulvert#268471Launching the culvert program592026-09-18
AnsweredACulvert#268442All lines are displayed as dashed lines, what should I do?1402026-09-17
AnsweredACulvert#268429Question about U-type underpass1262026-09-17
AnsweredACulvert#268424Load position when applying railway loads to an underpass2372026-09-17
AnsweredACulvert#268417Changing girder dimensions1522026-09-17
AnsweredACulvert#268396Incorrect section check location for horizontal rebar1842026-09-16
AnsweredACulvert#268376Question about segment settings for U-type retaining wall1942026-09-15
AnsweredACulvert#268343Question about culvert drawing output1292026-09-15
AnsweredACulvert#268337Inquiry about checking retaining-wall-type wing walls3062026-09-14
AnsweredACulvert#268330About drawing output1542026-09-14
AnsweredACulvert#268318Some blocks not displayed1412026-09-14
AnsweredACulvert#268317Tank load for surcharge and moving loads3422026-09-14
Sign in to ask