AnsweredACulvertQ&A #2251342004-08-05 20:09 · Views 64

Load factors for railway (roadbed)

안녕하세요. 첨부화일에서 하중계수가 잘못 적용된것 같습니다. 확인 부탁합니다.. ^^ 조은하루 보내세요

Answer

안녕하세요. 한길아이티입니다. 전화상으로 말씀드렸습니다. 고정하중계수를 토피가 없을경우엔 1.4로 토피가 있을 경우엔 1.54로 하중조합에 적용되고 있습니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredACulvert#268543Pile calculation report3292026-09-28
AnsweredACulvert#268536Setting section changes in culvert1742026-09-28
AnsweredACulvert#268524Design check not performed at wall center2172026-09-27
AnsweredACulvert#268523Applying moving vehicle loads2392026-09-27
AnsweredACulvert#268522Question about pile layout2632026-09-23
AnsweredACulvert#268521Question about features1302026-09-23
AnsweredACulvert#268510Question about joint check in Excel report output1852026-09-22
AnsweredACulvert#268499Error in STM analysis of corner region1442026-09-22
AnsweredACulvert#268471Launching the culvert program592026-09-18
AnsweredACulvert#268442All lines are displayed as dashed lines, what should I do?1402026-09-17
AnsweredACulvert#268429Question about U-type underpass1262026-09-17
AnsweredACulvert#268424Load position when applying railway loads to an underpass2372026-09-17
AnsweredACulvert#268417Changing girder dimensions1522026-09-17
AnsweredACulvert#268396Incorrect section check location for horizontal rebar1842026-09-16
AnsweredACulvert#268376Question about segment settings for U-type retaining wall1942026-09-15
AnsweredACulvert#268343Question about culvert drawing output1292026-09-15
AnsweredACulvert#268337Inquiry about checking retaining-wall-type wing walls3062026-09-14
AnsweredACulvert#268330About drawing output1542026-09-14
AnsweredACulvert#268318Some blocks not displayed1412026-09-14
AnsweredACulvert#268317Tank load for surcharge and moving loads3422026-09-14
Sign in to ask