Please check the wall rebar

(7+579)암거를 보시면 벽체중앙부 외측에 모멘트가 발생하여 외측에 두번째cycle도 철근을 이음을 주려고 하는데요..철근연결이음을 선택하면 철근이 없어집니다. 그리고 상부(상단)에서도 두번째cycle에서 이음을 주면 이음위치가 안나오고 철근하나로 나오던데 첫번째cycle처럼 이음위치하고 길이를 설정할수는 없나요?

Answer

안녕하세요. 한길아이티입니다. 벽체중앙의 철근이음에 관한 오류를 확인하였습니다. 또한 2 cycle에서 철근 이음을 주었을때 적용철근길이인 8m나 10m가 넘을경우 겹이음 위치에 입력사항은 아직 지원이 안되고 작업중에 있습니다. 조속한 시일내에 패치에 반영하겠습니다. 사용에 불편을 드려 대단히 죄송합니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredACulvert#268543Pile calculation report3292026-09-28
AnsweredACulvert#268536Setting section changes in culvert1742026-09-28
AnsweredACulvert#268524Design check not performed at wall center2172026-09-27
AnsweredACulvert#268523Applying moving vehicle loads2392026-09-27
AnsweredACulvert#268522Question about pile layout2662026-09-23
AnsweredACulvert#268521Question about features1302026-09-23
AnsweredACulvert#268510Question about joint check in Excel report output1852026-09-22
AnsweredACulvert#268499Error in STM analysis of corner region1442026-09-22
AnsweredACulvert#268471Launching the culvert program592026-09-18
AnsweredACulvert#268442All lines are displayed as dashed lines, what should I do?1402026-09-17
AnsweredACulvert#268429Question about U-type underpass1262026-09-17
AnsweredACulvert#268424Load position when applying railway loads to an underpass2372026-09-17
AnsweredACulvert#268417Changing girder dimensions1522026-09-17
AnsweredACulvert#268396Incorrect section check location for horizontal rebar1842026-09-16
AnsweredACulvert#268376Question about segment settings for U-type retaining wall1942026-09-15
AnsweredACulvert#268343Question about culvert drawing output1292026-09-15
AnsweredACulvert#268337Inquiry about checking retaining-wall-type wing walls3062026-09-14
AnsweredACulvert#268330About drawing output1542026-09-14
AnsweredACulvert#268318Some blocks not displayed1412026-09-14
AnsweredACulvert#268317Tank load for surcharge and moving loads3422026-09-14
Sign in to ask