설계조건의 기초 형식이 P2,P4이 우물통 기초 인데 P2작업중 모든 교각동일 적용 하였더니 내부오류가 발생 하였습니다.

Answer

안녕하세요. 한길아이티입니다. 단일현장타설 말뚝으로 설정하신것으로 판단되며, 오류부분을 수정하여 금일중 패치하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#207713Please check392007-10-26
AnsweredAAbutPier#207710Pier bearing seat reinforcement detailing442007-10-26
AnsweredAAbutPier#207703Drawing representation for varying mass concrete length?682007-10-26
AnsweredAAbutPier#207701Internal error · Currently viewing592007-10-26
AnsweredAAbutPier#207699Error when generating calculation report92007-10-26
AnsweredAAbutPier#207692Pier bearing seat reinforcement detailing322007-10-26
AnsweredAAbutPier#207690Edge distance check does not work302007-10-26
AnsweredAAbutPier#207707Abutment shear rebar check, pier foundation reinforcement design check, frame analysis392007-10-26
AnsweredAAbutPier#207700*** ***92007-10-26
AnsweredAAbutPier#207698Separation distance between up and down lines162007-10-26
AnsweredAAbutPier#207688Error in balanced reinforcement ratio formula232007-10-26
AnsweredAAbutPier#207687Seismic modeling error when adding a bridge342007-10-26
AnsweredAAbutPier#207686Does this change with the upgrade?452007-10-26
AnsweredAAbutPier#207684Internal error262007-10-26
AnsweredAAbutPier#207667Horizontal force values look wrong after frame analysis552007-10-25
AnsweredAAbutPier#207682Question on applying section forces542007-10-25
AnsweredAAbutPier#207676Rounded pier coping?402007-10-25
AnsweredAAbutPier#207674Seismic check282007-10-25
AnsweredAAbutPier#207673ARoad *.sbi compatibility and quantity summary error842007-10-25
AnsweredAAbutPier#207663Calculation report also attached322007-10-25
Sign in to ask