Plastic design - confinement rebar quantity check error
소성설계 (P2) 에서 심부구속량 산정시 심부구속구간에 75mm 간격으로 철근을 배근했는데, 검토시에는 일반구간에 배근된 띠철근량 (간격300mm) 으로 검토 되고 있습니다.. 빨리 해야 하는데 중간중간 문제점들이 너무 많이 생기네요.. 빠른 검토 부탁드립니다..
Answer
안녕하세요. 한길아이티입니다. 출력부분에 오류가 있었으며 수정하여 금일중으로 패치하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #207106 | When entering shear and distribution rebar | 20 | 2007-10-12 |
| Answered | AAbutPier | #207102 | Bearing seat detail "A" not output | 19 | 2007-10-12 |
| Answered | AAbutPier | #207101 | Plastic design - confinement rebar quantity check error · Currently viewing | 27 | 2007-10-12 |
| Answered | AAbutPier | #207091 | Abnormal Vu value after applying patch | 17 | 2007-10-11 |
| Answered | AAbutPier | #207088 | Abutment bearing seat elevation wrong again | 28 | 2007-10-11 |
| Answered | AAbutPier | #207078 | Coping step location | 20 | 2007-10-11 |
| Answered | AAbutPier | #207074 | Column check error | 41 | 2007-10-11 |
| Answered | AAbutPier | #207069 | Vu value is "0" in corbel (deep beam) check | 30 | 2007-10-11 |
| Answered | AAbutPier | #207107 | Bearing spring constant issue in seismic analysis | 15 | 2007-10-11 |
| Answered | AAbutPier | #207096 | Rebar quantity below bridge bearing differs between program and Excel sheet | 18 | 2007-10-11 |
| Answered | AAbutPier | #207092 | Discrepancy in seismic horizontal force between start and end abutments | 40 | 2007-10-11 |
| Answered | AAbutPier | #207070 | Shear and distribution rebar error | 59 | 2007-10-11 |
| Answered | AAbutPier | #207048 | Seismic error | 32 | 2007-10-11 |
| Answered | AAbutPier | #207045 | Girder layout program error | 34 | 2007-10-11 |
| Answered | AAbutPier | #207036 | APR file for post 30485 | 21 | 2007-10-11 |
| Answered | AAbutPier | #207030 | Skewed abutment design | 61 | 2007-10-10 |
| Answered | AAbutPier | #207021 | Designing a bridge modified from an existing bridge | 16 | 2007-10-10 |
| Answered | AAbutPier | #207018 | Seismic analysis modeling error | 18 | 2007-10-10 |
| Answered | AAbutPier | #207037 | Abutment calculation report inquiry | 22 | 2007-10-10 |
| Answered | AAbutPier | #207020 | Wing wall reinforcement drawing and rebar schedule do not match | 27 | 2007-10-10 |