Abutment calculation report inquiry
전에 올린것은 A2를 켑쳐한것 같은데 A1을 다시 켑쳐해서 올립니다. A1도 교대계산서 철근량 검토에서 Mu값이 프로그램에서 나온값과 다름
Answer
안녕하세요. 한길아이티입니다. 질의하신 내용 검토중이며 완료시 답변하도록 하겠습니다. 감사합니다. 안녕하세요. 한길아이티입니다. 수정하여 금일중으로 패치하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #207106 | When entering shear and distribution rebar | 20 | 2007-10-12 |
| Answered | AAbutPier | #207102 | Bearing seat detail "A" not output | 19 | 2007-10-12 |
| Answered | AAbutPier | #207101 | Plastic design - confinement rebar quantity check error | 27 | 2007-10-12 |
| Answered | AAbutPier | #207091 | Abnormal Vu value after applying patch | 17 | 2007-10-11 |
| Answered | AAbutPier | #207088 | Abutment bearing seat elevation wrong again | 28 | 2007-10-11 |
| Answered | AAbutPier | #207078 | Coping step location | 20 | 2007-10-11 |
| Answered | AAbutPier | #207074 | Column check error | 41 | 2007-10-11 |
| Answered | AAbutPier | #207069 | Vu value is "0" in corbel (deep beam) check | 30 | 2007-10-11 |
| Answered | AAbutPier | #207107 | Bearing spring constant issue in seismic analysis | 15 | 2007-10-11 |
| Answered | AAbutPier | #207096 | Rebar quantity below bridge bearing differs between program and Excel sheet | 18 | 2007-10-11 |
| Answered | AAbutPier | #207092 | Discrepancy in seismic horizontal force between start and end abutments | 40 | 2007-10-11 |
| Answered | AAbutPier | #207070 | Shear and distribution rebar error | 59 | 2007-10-11 |
| Answered | AAbutPier | #207048 | Seismic error | 32 | 2007-10-11 |
| Answered | AAbutPier | #207045 | Girder layout program error | 34 | 2007-10-11 |
| Answered | AAbutPier | #207036 | APR file for post 30485 | 21 | 2007-10-11 |
| Answered | AAbutPier | #207030 | Skewed abutment design | 61 | 2007-10-10 |
| Answered | AAbutPier | #207021 | Designing a bridge modified from an existing bridge | 16 | 2007-10-10 |
| Answered | AAbutPier | #207018 | Seismic analysis modeling error | 18 | 2007-10-10 |
| Answered | AAbutPier | #207037 | Abutment calculation report inquiry · Currently viewing | 22 | 2007-10-10 |
| Answered | AAbutPier | #207020 | Wing wall reinforcement drawing and rebar schedule do not match | 27 | 2007-10-10 |