Wing wall reinforcement drawing
날개벽 배근도에서 철근배근이 빠진 곳이 있습니다. 어떻게 해야 합니까? *. 교대배근도 08번 도면
Answer
안녕하세요. 한길아이티입니다. 도면생성전 특히 배근도관련해서는 철근제원에서 권고안을 실행한뒤 도면을 생성하셔야 합니다. 올려주신 화일도 철근제원에서 권고안을 실행하면 배근에 문제가 없어지게 됩니다. 화일을 올려드리니 참고하시기 바랍니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #206536 | Wing wall reinforcement drawing · Currently viewing | 24 | 2007-09-27 |
| Answered | AAbutPier | #206534 | About pile checks | 35 | 2007-09-27 |
| Answered | AAbutPier | #206529 | Seismic analysis modeling | 15 | 2007-09-27 |
| Answered | AAbutPier | #206525 | Superstructure seismic load is excessive | 13 | 2007-09-27 |
| Answered | AAbutPier | #206527 | Seismic analysis modeling | 25 | 2007-09-27 |
| Answered | AAbutPier | #206522 | Inner rebar | 20 | 2007-09-23 |
| Answered | AAbutPier | #206521 | When checking columns | 47 | 2007-09-22 |
| Answered | AAbutPier | #206520 | Internal program error | 23 | 2007-09-21 |
| Answered | AAbutPier | #206517 | Seismic check | 27 | 2007-09-21 |
| Answered | AAbutPier | #206516 | Quantity calculation error | 13 | 2007-09-21 |
| Answered | AAbutPier | #206514 | Applying bridge bearing dimensions | 34 | 2007-09-21 |
| Answered | AAbutPier | #206509 | Question about EPS backfill | 41 | 2007-09-21 |
| Answered | AAbutPier | #206503 | About coping check | 71 | 2007-09-21 |
| Answered | AAbutPier | #206511 | Bearing layout drawing for single-span bridge | 37 | 2007-09-21 |
| Answered | AAbutPier | #206494 | When checking wing wall sections | 36 | 2007-09-21 |
| Answered | AAbutPier | #206488 | Please check coping reinforcement detailing | 17 | 2007-09-21 |
| Answered | AAbutPier | #206483 | Question (error?) about SAP modeling in seismic analysis | 18 | 2007-09-21 |
| Answered | AAbutPier | #206479 | Span configuration is not applied | 29 | 2007-09-20 |
| Answered | AAbutPier | #206493 | Inquiry about pier output drawings | 18 | 2007-09-20 |
| Answered | AAbutPier | #206480 | Dot rebar representation | 35 | 2007-09-20 |