Superelevation calculation program error
현재 화면(교량 기본 구성 입력)에서 편구배 계산서 출력시 내부 응용프로그램 오류가 뜨며, 입력한 편구배값이 적용 되지 않은채 설계가 됩니다. 왜 그런지 답변 부탁드립니다. 항상 부탁 드리는 거지만 빨리 좀....^^;
Answer
안녕하세요. 한길아이티입니다. 올려주신화일에 선형화일내보내기를 실행하여 보면 선형에 대한 정보 평면선형,종단선형,편경사 입력이 잘못되어 있읍니다. 선형내용을 확인후 이상이 발견되면 다시 올려주시기 바랍니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #206112 | Request to check pier cap dimensions and column tie bar layout | 31 | 2007-09-06 |
| Answered | AAbutPier | #206111 | Widening at pier center in R bridge | 31 | 2007-09-06 |
| Answered | AAbutPier | #206109 | Superelevation calculation program error · Currently viewing | 11 | 2007-09-06 |
| Answered | AAbutPier | #206113 | Post 29526 resolved | 52 | 2007-09-05 |
| Answered | AAbutPier | #206110 | Not recognized | 31 | 2007-09-05 |
| Answered | AAbutPier | #206107 | Question about seismic design | 40 | 2007-09-05 |
| Answered | AAbutPier | #206102 | Why the foundation analysis does not run | 35 | 2007-09-05 |
| Answered | AAbutPier | #206100 | Why the seismic analysis does not run? | 24 | 2007-09-05 |
| Answered | AAbutPier | #206096 | Reinforcement not entered when using two layers of main rebar in abutment footing heel | 24 | 2007-09-05 |
| Answered | AAbutPier | #206095 | Why the seismic analysis does not run? | 25 | 2007-09-05 |
| Answered | AAbutPier | #206091 | Attaching the file below | 19 | 2007-09-04 |
| Answered | AAbutPier | #206080 | About bearings | 39 | 2007-09-04 |
| Answered | AAbutPier | #206068 | Shouldn't the larger value be applied for superstructure inertia (horizontal) force? | 74 | 2007-09-04 |
| Answered | AAbutPier | #206063 | Inquiry about pier end beam dimensions (bearing locations) | 14 | 2007-09-03 |
| Answered | AAbutPier | #206060 | Bridge bearing horizontal force is too large | 40 | 2007-09-03 |
| Answered | AAbutPier | #206078 | Manual input | 26 | 2007-09-03 |
| Answered | AAbutPier | #206075 | N-value at pile head | 23 | 2007-09-03 |
| Answered | AAbutPier | #206054 | Error when creating sapdata for seismic analysis | 39 | 2007-09-03 |
| Answered | AAbutPier | #206073 | New employee of 4 months | 48 | 2007-09-03 |
| Answered | AAbutPier | #206059 | Quantity calculation report | 34 | 2007-09-03 |