AnsweredAAbutPierQ&A #2061022007-09-05 01:57 · Views 35

Why the foundation analysis does not run

일반적인 교대보다 앞굽과 뒷굽이 긴 교량입니다. 설계검토가 안되네여. 검토부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 교대기초부설정입력에서 말뚝두께가 입력이 누락되어 기초검토시 말뚝반력이 잘못산정되서 생기는 문제입니다. 누락된부분을 입력하시기 바랍니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#206112Request to check pier cap dimensions and column tie bar layout312007-09-06
AnsweredAAbutPier#206111Widening at pier center in R bridge312007-09-06
AnsweredAAbutPier#206109Superelevation calculation program error112007-09-06
AnsweredAAbutPier#206113Post 29526 resolved522007-09-05
AnsweredAAbutPier#206110Not recognized312007-09-05
AnsweredAAbutPier#206107Question about seismic design402007-09-05
AnsweredAAbutPier#206102Why the foundation analysis does not run · Currently viewing352007-09-05
AnsweredAAbutPier#206100Why the seismic analysis does not run?242007-09-05
AnsweredAAbutPier#206096Reinforcement not entered when using two layers of main rebar in abutment footing heel242007-09-05
AnsweredAAbutPier#206095Why the seismic analysis does not run?252007-09-05
AnsweredAAbutPier#206091Attaching the file below192007-09-04
AnsweredAAbutPier#206080About bearings392007-09-04
AnsweredAAbutPier#206068Shouldn't the larger value be applied for superstructure inertia (horizontal) force?742007-09-04
AnsweredAAbutPier#206063Inquiry about pier end beam dimensions (bearing locations)142007-09-03
AnsweredAAbutPier#206060Bridge bearing horizontal force is too large402007-09-03
AnsweredAAbutPier#206078Manual input262007-09-03
AnsweredAAbutPier#206075N-value at pile head232007-09-03
AnsweredAAbutPier#206054Error when creating sapdata for seismic analysis392007-09-03
AnsweredAAbutPier#206073New employee of 4 months482007-09-03
AnsweredAAbutPier#206059Quantity calculation report342007-09-03
Sign in to ask