Question about live load in bearing area check
안녕하십니까? 구조계산서에서 의문점이 있어서 문의드립니다. 첨부한 구조계산서 화일에서 9.교좌부검토 4)교량받침하면보강 에서 -연직하중 : 고정하중 + 활하중 P= 2237.126 + 844.694 = 3081.820 kN 문의드립니다. 위 산정식에서 활하중에 대한 산출근거를 알고 싶습니다. (참고적으로, 고정하중은 2.단면가정 *교량 받침 집계표에 명기되어있으나, 집계표에서의 활하중과 교좌부검토시 활하중이 불일치합니다.) 이상입니다. 수고하십시요.
Answer
안녕하세요. 한길아이티입니다. xls화일과 apr화일을 같이 올려주셔야지 검토가 가능합니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #205829 | Drawing text | 77 | 2007-08-17 |
| Answered | AAbutPier | #205831 | When will the MASS foundation sliding check be updated? | 62 | 2007-08-17 |
| Answered | AAbutPier | #205826 | About the foundation | 60 | 2007-08-17 |
| Answered | AAbutPier | #205825 | Question about live load in bearing area check · Currently viewing | 80 | 2007-08-17 |
| Answered | AAbutPier | #205823 | Horizontal force calculation | 55 | 2007-08-17 |
| Answered | AAbutPier | #205819 | Please merge two files | 73 | 2007-08-17 |
| Answered | AAbutPier | #205812 | Additional pier file | 61 | 2007-08-17 |
| Answered | AAbutPier | #205810 | Question about the number of bearings | 33 | 2007-08-16 |
| Answered | AAbutPier | #205809 | Earth pressure calculation error in MASS foundation stability check | 39 | 2007-08-16 |
| Answered | AAbutPier | #205808 | Quantity (rebar) | 40 | 2007-08-16 |
| Answered | AAbutPier | #205805 | Errors in pier column reinforcement detailing and coping | 51 | 2007-08-16 |
| Answered | AAbutPier | #205794 | Pier modeling analysis error | 32 | 2007-08-14 |
| Answered | AAbutPier | #205792 | Maximum rebar ratio check formula is applied incorrectly | 37 | 2007-08-14 |
| Answered | AAbutPier | #205789 | Cannot enter cover thickness | 62 | 2007-08-14 |
| Answered | AAbutPier | #205786 | About entering the unit weight of embankment material | 29 | 2007-08-14 |
| Answered | AAbutPier | #205781 | Internal error during pile check | 22 | 2007-08-14 |
| Answered | AAbutPier | #205770 | When applying stepped rebar to a pier | 46 | 2007-08-14 |
| Answered | AAbutPier | #205764 | Cannot enter the number of columns in pier section dimensions | 37 | 2007-08-13 |
| Answered | AAbutPier | #205763 | Please check the pile layout | 29 | 2007-08-13 |
| Answered | AAbutPier | #205759 | Uploading captured images and file | 40 | 2007-08-13 |