Skip to content
AnsweredAAbutPierQ&A #2009762006-11-09 20:50 · Views 54

In pile cap beam reinforcement

교각설계에서 두부보 배근 오류가 있는것 같습니다 콘크리트밖으로 나온 철근도 있고 안쪽에 배근 안되는 부분도 있네요 확인해주세용 파일 첨부합니다

Answer

안녕하세요. 한길아이티입니다. 보내주신 코핑상단의 형태는 현재 지원하지 않고 있읍니다. 현재개발중인 APIER II에서는 지원할예정입니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#201046Foundation reinforcement detailing and quantities442006-11-14
AnsweredAAbutPier#201043Please check my file392006-11-14
AnsweredAAbutPier#201047*** changing fonts582006-11-14
AnsweredAAbutPier#201037Two-layer main rebar in abutment wing walls342006-11-14
AnsweredAAbutPier#201033Question about rebar length402006-11-13
AnsweredAAbutPier#201040When generating drawing numbers442006-11-13
AnsweredAAbutPier#201034About rebar anchorage522006-11-13
AnsweredAAbutPier#201022In the foundation stability check782006-11-13
AnsweredAAbutPier#201013In the pier design conditions652006-11-11
AnsweredAAbutPier#201011Earthwork quantity752006-11-11
AnsweredAAbutPier#200997Question on main and distribution rebar in the abutment coping under the bearing seat532006-11-10
AnsweredAAbutPier#200999Problem calculating foundation displacement722006-11-10
AnsweredAAbutPier#200991Please check the count712006-11-10
AnsweredAAbutPier#200993Please check the styrofoam quantity672006-11-10
AnsweredAAbutPier#200979Wing wall reinforcement error patch592006-11-09
AnsweredAAbutPier#200976In pile cap beam reinforcement · Currently viewing542006-11-09
AnsweredAAbutPier#200992Two-column pier with isolated footings842006-11-09
AnsweredAAbutPier#200982Help not displaying472006-11-09
AnsweredAAbutPier#200972Error in seismic modeling analysis362006-11-09
AnsweredAAbutPier#200967Seismic application282006-11-09
Sign in to ask