Abutment wall rebar is detailed incorrectly
안녕하세요 수고 많으십니다. 교대 전면 주철근(W2)가 교대A1에서 흉벽까지 배근되어 정면도에 나타납니다. 검토좀 부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 교대벽체부 배근입력에서 권고안을 누르시면 일반도에 맞게 배근도가 초기화됩니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #200957 | Please check abutment front view width!!! | 48 | 2006-11-09 |
| Answered | AAbutPier | #200951 | Question about reinforcement drawing | 56 | 2006-11-09 |
| Answered | AAbutPier | #200950 | Error when generating reinforcement drawing | 36 | 2006-11-09 |
| Answered | AAbutPier | #200948 | Question on lap splice length of top and bottom rebar in approach slab | 42 | 2006-11-09 |
| Answered | AAbutPier | #200945 | Piers 1 and 4 | 62 | 2006-11-08 |
| Answered | AAbutPier | #200943 | Wing wall 4 | 62 | 2006-11-08 |
| Answered | AAbutPier | #200939 | After installing the patch update | 64 | 2006-11-08 |
| Answered | AAbutPier | #200931 | Wing wall reinforcement drawing issue | 85 | 2006-11-07 |
| Answered | AAbutPier | #200940 | About allowable pile bearing capacity | 49 | 2006-11-07 |
| Answered | AAbutPier | #200925 | Longitudinal load from continuous welded rail | 178 | 2006-11-07 |
| Answered | AAbutPier | #200920 | Please check the coordinate file | 51 | 2006-11-07 |
| Answered | AAbutPier | #200914 | Seismic SAP input file gives an error | 50 | 2006-11-07 |
| Answered | AAbutPier | #200910 | Eccentricity check at pier | 57 | 2006-11-07 |
| Answered | AAbutPier | #200909 | Wing wall rebar 2 | 34 | 2006-11-07 |
| Answered | AAbutPier | #200908 | Wing wall rebar | 36 | 2006-11-07 |
| Answered | AAbutPier | #200906 | Error when generating foundation SAP file | 32 | 2006-11-07 |
| Answered | AAbutPier | #200903 | Abutment wall rebar is detailed incorrectly · Currently viewing | 40 | 2006-11-06 |
| Answered | AAbutPier | #200898 | File won't open | 38 | 2006-11-06 |
| Answered | AAbutPier | #200919 | Wing wall 3 | 54 | 2006-11-06 |
| Answered | AAbutPier | #200897 | File won't open | 32 | 2006-11-06 |