Calculating a pier
벽식교각을 적용할려고 하는데요 교각은 하단의 폭이 2.5m이고 상단은 8.0m로 변단면입니다 제가 두부보의 제원을 대충입력하고 설계검토를 누르면 SAP은 해석이 다 되고요....창을 닫으면 검토결과 화면이 떠야하는데... 그부분에서 자꾸 다운이 됩니다... 벽식교각은 처음이라...제가 입력한 부분에서 에러가 있는건지...확인 좀 부탁드립니다. 제 연락처는 [개인정보]입니다... 조금 급한 일이라 빠른 답변 부탁드립니다..수고하세요
Answer
안녕하세요. 한길아이티입니다. 교각기둥부 주철근입력이 누락되어있어서 다운이 되는것입니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #199595 | Seismic analysis | 13 | 2006-08-10 |
| Answered | AAbutPier | #199593 | Phone inquiry | 21 | 2006-08-10 |
| Answered | AAbutPier | #199590 | Calculating a pier · Currently viewing | 21 | 2006-08-10 |
| Answered | AAbutPier | #199587 | Designing an approach bridge | 9 | 2006-08-10 |
| Answered | AAbutPier | #199586 | Please check the seismic force | 8 | 2006-08-10 |
| Answered | AAbutPier | #199584 | About slab dimensions | 11 | 2006-08-10 |
| Answered | AAbutPier | #199585 | Text size in drawing output | 20 | 2006-08-10 |
| Answered | AAbutPier | #199579 | Program error | 8 | 2006-08-10 |
| Answered | AAbutPier | #199571 | Question about temperature load | 14 | 2006-08-09 |
| Answered | AAbutPier | #199581 | Pier design options inquiry | 13 | 2006-08-09 |
| Answered | AAbutPier | #199568 | Entering shoe spacing | 27 | 2006-08-09 |
| Answered | AAbutPier | #199565 | Reinforcement below bridge bearings | 41 | 2006-08-09 |
| Answered | AAbutPier | #199562 | Abutment section dimensions | 8 | 2006-08-08 |
| Answered | AAbutPier | #199557 | Reinforcement below bridge bearings | 18 | 2006-08-08 |
| Answered | AAbutPier | #199554 | Entering wind load from top of ground level | 16 | 2006-08-08 |
| Answered | AAbutPier | #199548 | Program error | 23 | 2006-08-07 |
| Answered | AAbutPier | #199552 | Plastic design | 21 | 2006-08-07 |
| Answered | AAbutPier | #199545 | Question about alignment | 12 | 2006-08-07 |
| Answered | AAbutPier | #199544 | Please check | 24 | 2006-08-07 |
| Answered | AAbutPier | #199540 | Please check | 34 | 2006-08-05 |