About the approach slab

콘크리트 포장용 접속슬래브를 사용할 경우 fck=270kgf/cm2 의 콘크리트와 H-bar를 사용하게 되는데요... 이음장이 발생할 경우... D-bar의 겹이음 길이로 산출됩니다. 추가로... 첨부파일의 접속슬래브 도면에서 8번철근의 갯수가 좀 많이 산출되는듯한데... 검토부탁드립니다. 감사합니다.

Answer

안녕하세요. 한길아이티입니다. 말씀하신 사항은 확인하였습니다. 수정하여 금일자 패치에 적용하도록 하겠습니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#196741Please review122005-12-13
AnsweredAAbutPier#196737About pier reinforcement detailing162005-12-13
AnsweredAAbutPier#196736Inquiry about seismic analysis modeling error102005-12-13
AnsweredAAbutPier#196735Abutment reinforcement drawing112005-12-13
AnsweredAAbutPier#196730Modeling when running seismic analysis132005-12-13
AnsweredAAbutPier#196731About rebar reinforcement detailing132005-12-13
AnsweredAAbutPier#196726In seismic analysis62005-12-13
AnsweredAAbutPier#196723Question about main rebar in railway bridge abutment foundation52005-12-13
AnsweredAAbutPier#196717Abutment ELEVATION172005-12-13
AnsweredAAbutPier#196716About column moment magnification532005-12-13
AnsweredAAbutPier#196715About the approach slab · Currently viewing192005-12-13
AnsweredAAbutPier#196713Error generating seismic input data102005-12-12
AnsweredAAbutPier#196707Reinforcement drawing error132005-12-12
AnsweredAAbutPier#196706Please check rebar spacing on the buffer slab drawing112005-12-12
AnsweredAAbutPier#196694Seismic calculation report output error72005-12-09
AnsweredAAbutPier#196688Check of distribution rebar diameter in approach slab92005-12-09
AnsweredAAbutPier#196684Pile layout error192005-12-09
AnsweredAAbutPier#196685Abutment wall surface finishing rebar232005-12-09
AnsweredAAbutPier#196680Abutment foundation rebar detailing looks wrong162005-12-09
AnsweredAAbutPier#196675Pile quantity112005-12-08
Sign in to ask