In pier reinforcement drawing (1)
교각배근도(1)번에서 띠철근 배근시 구간을 4구간으로 하여 배근하였으나.현재 도면상에 표시되는 치수는 3구간의 치수가 표현되지 않네요..교각의 높이가 높아서 그런건지 확인바랍니다.수고하세요!
Answer
안녕하세요. 한길아이티입니다. 교각 절단 표현시 중앙부 절단 옵션이 적용되어 2번구간이 사라져서 생긴 현상입니다. [교각입력] - [설계환경] - [설계선택사항] - "교각표현시 기둥부 철근 절단표현 방법"을 각 구간별 비율적용 절단으로 선택하시면, 모든 구간이 같은 비율로 절단되어 사라지는 구간 없이 모두 표현이 됩니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #194386 | About shear rebar calculation for columns.. | 30 | 2005-09-03 |
| Answered | AAbutPier | #194384 | Wing wall and parapet reinforcing rebar | 25 | 2005-09-03 |
| Answered | AAbutPier | #194379 | Entering step rebar in the coping | 57 | 2005-09-03 |
| Answered | AAbutPier | #194368 | Seismic horizontal force is excessively large | 37 | 2005-09-02 |
| Answered | AAbutPier | #194373 | Design conditions? | 34 | 2005-09-02 |
| Answered | AAbutPier | #194358 | Abutment wing wall section thickness transition zone | 40 | 2005-09-02 |
| Answered | AAbutPier | #194354 | Seismic analysis | 39 | 2005-09-01 |
| Answered | AAbutPier | #194352 | About SAP2000 auto-run | 60 | 2005-09-01 |
| Answered | AAbutPier | #194347 | In pier reinforcement drawing (1) · Currently viewing | 40 | 2005-09-01 |
| Answered | AAbutPier | #194343 | Cannot place cross beams | 41 | 2005-09-01 |
| Answered | AAbutPier | #194341 | Bearing pedestal concrete and shoe location | 46 | 2005-09-01 |
| Answered | AAbutPier | #194340 | Uploading the Osaek pedestrian overpass | 29 | 2005-09-01 |
| Answered | AAbutPier | #194333 | Urgent question about earthwork | 26 | 2005-09-01 |
| Answered | AAbutPier | #194332 | Pier section forces come out 1.5 times higher | 35 | 2005-09-01 |
| Answered | AAbutPier | #194328 | Bridge bearings | 18 | 2005-08-31 |
| Answered | AAbutPier | #194321 | Error during seismic analysis | 32 | 2005-08-31 |
| Answered | AAbutPier | #194320 | Elevation looks wrong | 38 | 2005-08-31 |
| Answered | AAbutPier | #194311 | Please review | 17 | 2005-08-31 |
| Answered | AAbutPier | #194317 | Uploading Osaek pedestrian overpass data | 28 | 2005-08-31 |
| Answered | AAbutPier | #194301 | Approach slab drawing outputs incorrectly | 23 | 2005-08-30 |