In the abutment general drawing
평면도와 단면도의 도로중심선 위치가 일치하지 않습니다. 종점부 교대의 평면도를 보시면 도로중심선이 제 위치에 있지 않습니다. 검토바랍니다
Answer
안녕하세요. 한길아이티입니다. 수정하였습니다. 금일자 패치에 적용하도록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #189176 | Pier structural drawing | 23 | 2004-11-18 |
| Answered | AAbutPier | #189168 | Soil cover load on pier | 60 | 2004-11-17 |
| Answered | AAbutPier | #189167 | Calculation report - bearing area check | 43 | 2004-11-17 |
| Answered | AAbutPier | #189163 | Applying soil cover load on pier | 29 | 2004-11-17 |
| Answered | AAbutPier | #189162 | Abutment parapet distribution bar issue | 39 | 2004-11-17 |
| Answered | AAbutPier | #189179 | Wind load intensity considering noise barrier | 50 | 2004-11-17 |
| Answered | AAbutPier | #189178 | Moment due to dead load and moment due to wind load | 21 | 2004-11-17 |
| Answered | AAbutPier | #189175 | Request | 23 | 2004-11-17 |
| Answered | AAbutPier | #189174 | Pier cap check | 16 | 2004-11-17 |
| Answered | AAbutPier | #189173 | About sketches in quantity calculation | 18 | 2004-11-17 |
| Answered | AAbutPier | #189172 | Please review | 28 | 2004-11-17 |
| Answered | AAbutPier | #189171 | Abutment wing wall rebar looks wrong | 24 | 2004-11-17 |
| Answered | AAbutPier | #189158 | Pier reinforcement drawing | 31 | 2004-11-17 |
| Answered | AAbutPier | #189150 | Follow-up question | 30 | 2004-11-17 |
| Answered | AAbutPier | #189147 | Abutment footing plan reinforcement and design settings | 35 | 2004-11-17 |
| Answered | AAbutPier | #189144 | Please check abutment road centerline dimensions | 34 | 2004-11-16 |
| Answered | AAbutPier | #189143 | Please review | 49 | 2004-11-16 |
| Answered | AAbutPier | #189141 | Seismic and slab input | 38 | 2004-11-16 |
| Answered | AAbutPier | #189140 | In the abutment general drawing · Currently viewing | 52 | 2004-11-16 |
| Answered | AAbutPier | #189154 | Follow-up question | 32 | 2004-11-16 |