Skip to content
AnsweredAAbutPierQ&A #1889642004-11-05 23:48 · Views 25

Inquiry about scaffolding and scaffold stair quantities

교각 비계, 비계다리 수량이 산출되지 않고 있습니다. 검토 부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 수정하였습니다. 금일자 패치에 반영하도록 하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#188974Cross slope in abutment front view462004-11-06
AnsweredAAbutPier#188973Pier shoring quantity92004-11-06
AnsweredAAbutPier#188969Follow-up to my phone inquiry82004-11-06
AnsweredAAbutPier#188964Inquiry about scaffolding and scaffold stair quantities · Currently viewing252004-11-05
AnsweredAAbutPier#188953Pile cap beam1232004-11-05
AnsweredAAbutPier#188950Placing P.F beams on steep longitudinal grade562004-11-05
AnsweredAAbutPier#188975Drawing improvement suggestions362004-11-05
AnsweredAAbutPier#188959Inquiry462004-11-05
AnsweredAAbutPier#188958Distribution rebar position issue1442004-11-05
AnsweredAAbutPier#188947Uploading file, please take a look92004-11-05
AnsweredAAbutPier#188946About pile cap beam design232004-11-05
AnsweredAAbutPier#188942Abutment front view dimension input92004-11-05
AnsweredAAbutPier#188938Inquiry192004-11-05
AnsweredAAbutPier#188937Span configuration input is incorrect72004-11-05
AnsweredAAbutPier#188930Pier circular formwork quantity calculation error362004-11-04
AnsweredAAbutPier#188925About rebar dimensions242004-11-04
AnsweredAAbutPier#188923Multi-column pier column check in transverse direction992004-11-04
AnsweredAAbutPier#188921Check of horizontal force on pile cap beam1002004-11-04
AnsweredAAbutPier#188916Please check coping step362004-11-04
AnsweredAAbutPier#188909Internal application error112004-11-04