AnsweredAAbutPierQ&A #1888442004-11-02 01:19 · Views 29

Earthwork summary table does not match calculation basis

앞성토 집계가 산출근거와 맞지 않읍니다.

Answer

안녕하세요. 한길아이티입니다. Excel출력시는 정상적으로 나오나, AAbutPier상에서는 집계표와 산출근거가 다르게 출력되는 것을 확인하였습니다. 수정해서 패치에 적용하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#188906Column tie rebar input172004-11-04
AnsweredAAbutPier#188905Please check bearing stiffness values112004-11-04
AnsweredAAbutPier#188904Quantity report output takes too long, file attached172004-11-04
AnsweredAAbutPier#188901Abutment bridge bearing reinforcing rebar302004-11-04
AnsweredAAbutPier#188899Please check cross slope of skewed abutment52004-11-04
AnsweredAAbutPier#188898Seismic analysis field is not enabled62004-11-03
AnsweredAAbutPier#188894Shoe arrangement order seems different62004-11-03
AnsweredAAbutPier#188890How are dimensions calculated in the illustrations?42004-11-03
AnsweredAAbutPier#188902File for seismic design92004-11-03
AnsweredAAbutPier#188900[Personal information] Please check62004-11-03
AnsweredAAbutPier#188893About the program122004-11-03
AnsweredAAbutPier#188888Abutment structural calculation report - 4. Wall design error in section design82004-11-03
AnsweredAAbutPier#188878Seismic column section problem42004-11-03
AnsweredAAbutPier#188875*** File for the inquiry made by phone82004-11-03
AnsweredAAbutPier#188873Illustration error in quantity calculation report92004-11-03
AnsweredAAbutPier#188869***, please check the wing wall drawing112004-11-02
AnsweredAAbutPier#188867Internal program error?382004-11-02
AnsweredAAbutPier#188844Earthwork summary table does not match calculation basis · Currently viewing292004-11-02
AnsweredAAbutPier#188858Front wing wall input472004-11-01
AnsweredAAbutPier#188845Question about scaffolding ladder quantity202004-11-01
Sign in to ask