*** please check
현재..거더 자동배치를 적용하여 슈의 스테이션을 확인을 하는중 빔의 길이가 34.9가 나와야 하는데 34.95가 나옵니다. 확인 부탁드립니다..
Answer
안녕하세요. 한길아이티입니다. 검토결과 정확한 좌표 및 길이가 산출됩니다. 보내주신 수작업으로 작성한 캐드 파일에는 선형이 원곡선인데 P Line 처리되어 스테이션이 조금 짧게 나온것 같습니다. 정확한 원곡선으로 하여 다시 검토해 주시기 바랍니다. 의문 사항이 있으시면 전화 부탁드립니다. 부재중이라서 메모를 남겼습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #188600 | Substructure input data from *** | 9 | 2004-10-20 |
| Answered | AAbutPier | #188591 | Error when generating drawings | 11 | 2004-10-20 |
| Answered | AAbutPier | #188597 | Manual input of seismic values | 3 | 2004-10-20 |
| Answered | AAbutPier | #188595 | BRI file | 6 | 2004-10-20 |
| Answered | AAbutPier | #188581 | Error when creating the seismic design report | 31 | 2004-10-20 |
| Answered | AAbutPier | #188580 | Please check the quantities | 58 | 2004-10-19 |
| Answered | AAbutPier | #188589 | About pier column shear design | 11 | 2004-10-19 |
| Answered | AAbutPier | #188587 | About pier foundation structural calculation | 11 | 2004-10-19 |
| Answered | AAbutPier | #188573 | Re-uploading the file for top step rebar | 11 | 2004-10-19 |
| Answered | AAbutPier | #188572 | Question about tie rebar notation for wall-type piers | 9 | 2004-10-19 |
| Answered | AAbutPier | #188575 | About the pier column section | 16 | 2004-10-19 |
| Answered | AAbutPier | #188567 | Please reply | 21 | 2004-10-18 |
| Answered | AAbutPier | #188562 | *** please check · Currently viewing | 8 | 2004-10-18 |
| Answered | AAbutPier | #188561 | Quantity and drawing border | 19 | 2004-10-18 |
| Answered | AAbutPier | #188557 | Approach slab shape looks wrong | 22 | 2004-10-16 |
| Answered | AAbutPier | #188555 | Please review | 81 | 2004-10-16 |
| Answered | AAbutPier | #188556 | Vertical stiffeners | 56 | 2004-10-16 |
| Answered | AAbutPier | #188547 | Support request | 69 | 2004-10-16 |
| Answered | AAbutPier | #188546 | Shoe count incorrect since the October 15 update | 55 | 2004-10-16 |
| Answered | AAbutPier | #188545 | Pier temperature load calculation | 46 | 2004-10-16 |