Live load values for cross beams

안녕하세요~ 계산서7번 가로보 및 브레이싱검토 출력후 부재력값중 활하중값이 다 "0"으로 나오는데요.. 검토좀 부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 보내주신 입력 데이타로 검토해 보았습니다만 모두 "0"으로 나오네요. SAP2000을 별도로 실행해서 해석한 후 가로보를 클릭해 보았습니다. 여기서도 "0" 으로 나오고 있습니다. 따라서 현 상태에서 계산서는 문제 없어 보이네요. 수고하세요.

More in this list

StatusProductNo.TitleViewsDate
AnsweredARoad#127441Transverse distribution of dead load in single-box girder bridge3902014-07-02
AnsweredAAbutPier#127432Second-layer rebar in pier foundation placed outside first-layer rebar1962014-07-02
AnsweredAAbutPier#127431Second-layer rebar in pier foundation placed outside first-layer rebar2152014-07-02
AnsweredAAbutPier#127428Eccentric load changed after only changing abutment height and pier seismic load (bearings)2622014-07-01
AnsweredAAbutPier#127425Displacement of single cast-in-place pile1932014-07-01
Answered양배수장#127437I'd like to modify the shape of the discharge tank3052014-07-01
Answered#127430Live load values for cross beams · Currently viewing4212014-07-01
AnsweredARcBridge#1274292D frame analysis2042014-07-01
AnsweredABeamDeck#127420Rebar schedule not output correctly in cross beam calculation report figures and quantities4262014-07-01
AnsweredAAbutPier#127414Files won't open since the update2252014-07-01
AnsweredACulvert#127405Error importing MIDAS input2652014-06-30
AnsweredACulvert#127404Exterior wall section check1422014-06-30
AnsweredAWall#127421Request to upgrade design criteria4612014-06-30
AnsweredAAbutPier#127399Figure output1752014-06-30
AnsweredAAbutPier#127389Please check results for rotated pier foundation1832014-06-30
AnsweredACulvert#127418Left and right alignment of double-cell box1752014-06-30
AnsweredACulvert#127413Rebar numbers not shown in drawing output1722014-06-30
AnsweredACulvert#127402About the file1,0872014-06-30
AnsweredAAbutPier#127396AAbutPier 2014 installation error3722014-06-30
AnsweredACulvert#127381Inquiry (reposted with screen capture)2182014-06-28
Sign in to ask