AnsweredQ&A #1254922014-03-18 09:40 · Views 343

Rainfall intensity setting keeps changing

강우강도 지속시간을 5분에서 10분으로 정했는데 수리검토를 하면 5분 강우강도 값으로 변하여 계산이 됩니다. [개인정보] [개인정보] [개인정보]번으로 연락부탁드립니다.

Answer

유선상으로 답변드린것과 같이 Tc 값에 의해 강우강도가 계산이 되어 지므로 고객님께서 10분 값의 강우강도를 적용하시려면 유달거리 또는 유속의 조정을 통해 Tc를 10분으로 조정하시면 가능합니다. 수고하세요,

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#125550Column shear design7222014-03-20
AnsweredARcBridge#125549Distribution and diagonal reinforcement placement not output1972014-03-20
AnsweredACulvert#125540Rebar properties report an invalid argument but I can't find the cause1532014-03-20
AnsweredAAbutPier#125532Other quantities change after adding user quantities5912014-03-19
AnsweredACulvert#125522Skew reinforcement rebar placement2602014-03-19
AnsweredAAbutPier#125521Coping reinforcement detailing while entering pier input2252014-03-19
AnsweredARoad#125542Number of bolts and nuts in the internal entrance detail drawing1772014-03-19
AnsweredAAbutPier#125527Request for basic reference material on ductility design2602014-03-19
AnsweredABeamDeck#125520Drawings cannot be output3572014-03-19
AnsweredAAbutPier#125519Bottom rebar of the coping beam cannot be generated with the entered bottom round values2512014-03-19
AnsweredACulvert#125509Question about pile layout2202014-03-19
AnsweredARcBridge#125507Question about shoring quantity2312014-03-19
AnsweredACulvert#125505Shear check of approach slab1832014-03-18
AnsweredAAbutPier#125500Question on entering seismic load (column) for pier input1862014-03-18
AnsweredACulvert#125499Box culvert modeling1672014-03-18
AnsweredACulvert#125494Can lap splice length be adjusted manually in the main rebar assembly drawing?2222014-03-18
AnsweredACulvert#125493Reinforcement input error1932014-03-18
Answered#125511Error entering basic data4382014-03-18
Answered#125492Rainfall intensity setting keeps changing · Currently viewing3432014-03-18
AnsweredAAbutPier#125487Rebar ratio check2102014-03-18
Sign in to ask