AnsweredQ&A #1031682011-08-10 15:30 · Views 515

Slab reinforcement drawing error

슬래브 배근도가 제대로 도면생성이 안됨니다.

Answer

안녕하세요. 한길아이티입니다. 지적하신 부분은 수정했습니다. 자동업데이트 후 확인해 보시기 바랍니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredATypeDesign#103190Strut support issue on intermediate piles3132011-08-11
AnsweredARoad#103185Different lateral distribution results for additional loads3222011-08-11
AnsweredACulvert#103181Rebar quantity mismatch1822011-08-11
AnsweredACulvert#103180Question about main rebar layout1802011-08-11
AnsweredACulvert#103177Abnormally large safety factor2282011-08-11
AnsweredARcBridge#103166Section check: wall calculation results2802011-08-11
AnsweredAAbutPier#103160Foundation main rebar reinforcement detailing2922011-08-10
AnsweredAAbutPier#103184About abutment design settings2512011-08-10
AnsweredAAbutPier#103154Bracket rebar2222011-08-10
AnsweredACulvert#103149Quantity calculation report output error2572011-08-10
AnsweredARoad#103145Longitudinal moment caused by wind load2492011-08-10
AnsweredAAbutPier#103142Input of superstructure reactions2632011-08-10
AnsweredARoad#103141Wind load differences between AROAD 2008 and AROAD 20102332011-08-10
Answered#103168Slab reinforcement drawing error · Currently viewing5152011-08-10
AnsweredARoad#103167Longitudinal rib input per girder2312011-08-10
AnsweredARoad#103161Field splice detail2292011-08-10
AnsweredARoad#103155ARoad 2008 other loads2072011-08-10
AnsweredARoad#103153Request for a deliverables board2402011-08-10
AnsweredARoad#103150Wind load provisions2162011-08-10
AnsweredACulvert#103146When installing uplift restrainers2162011-08-10
Sign in to ask